Construction Progress
|
|
Update through March 9, 2007
Court and Cummings officials, pictured below during
one of their many collaborative design meetings, are zeroing in
on the fine details of the working drawings. Currently, the details,
such as the location of individual electrical receptacles, telephone
and data jacks, etc. are being sited on plans, and door and finish
schedules are being developed.
The finer points of the millwork for the 15 brand
new courtrooms, including the judges' benches, and the stations
for the court clerk, reporter, and court and probation officers,
as well as the jury boxes, are expected to be finalized by the end
of the month.

In the meantime, structural steel erection continues
at a brisk pace, surpassing the 50% completion plateau this past
week with the addition of the fifth and sixth floors on the north
portion of the courthouse. All of the pre-cast concrete panels for
the building exterior have been poured in Vermont, and are on track
for installation in late April, after steel erection is complete.
Contracts were recently awarded for the window walls
and other glass. Talks continue with the MBTA to bring public transportation
directly into Trade Center Park by the Court's move-in day, early
in 2008.
|
|
Update through February
22, 2007
Despite the arrival of winter weather
conditions several weeks ago, excellent progress continues at Trade
Center Park. The Courthouse foundation is now complete, along with
more than one-third of the parking garage foundation.
Indeed, steel frame erection and
decking assembly has been underway for almost two weeks and is already
about 20 percent complete. This work is being done in phases, and
notwithstanding some recent bitterly cold weather, four stories
of the first phase, on the north side of the building, are already
in place.
|
|
|
|
Drivers passing by on Route 128/I-95
are now able to see the frame of the Courthouse being erected. The
nearly 100 pre-cast architectural panels for this phase of the project
are fabricated and ready for installation when the steel frame is
done, expected around April 15.
The exhaustive construction drawings
that fully describe all aspects of the Courthouse construction have
also been advanced significantly by Cummings' in-house staff and
were delivered to Court officials this week. Designers from both
teams are now working closely to fine-tune the interior details.
Behind the scenes, crucial major
purchases are moving ahead quickly as well. For example, the contract
for the building's four elevators, including the dedicated elevators
for the judges and detainees was awarded this week. Next week the
contract for the expansive glass curtain wall will be awarded. Bid
packages have been issued for the concrete floors, fireproofing
and the roof.
|
|
|
|
|
Update through January 15, 2007
After taking advantage of at least
a little of Woburn's much delayed winter weather, active construction
is now well underway at Trade Center Park. The first steel pilings
went into the ground on January 2, and all of the Courthouse piles
are now in place.
The concrete pile caps, upon which
the building's steel framework will rise, are 90 percent complete
also, and the crews are making good progress already on the garage
foundation piles, as well. The perimeter foundation walls for the
Courthouse will likely be done by February 1.
Most of the structural steel is
already fabricated, and the erection contract has been awarded.
Steel erection is expected to begin by February 15, and installation
of the building's pre-cast concrete exterior should begin by April
15.
A special environmental study is
also being taken to identify "green building" options,
which Commonwealth authorities may want to consider for the building.
Because this Courthouse lease envisions an occupancy of only three
to five years, only those options which can pay for themselves within
the first 36 months will be presented.
These environmental-friendly options
include high-efficiency heat reflecting glass, especially for the
west side of the structure, and specially reflective white roofing.
Other fast-payback environmental upgrades to be recommended will
likely include construction of an on-site well to supply fresh ground
water, rather than City drinking water, for the Court's enormous
(200 ton) air-conditioning chillers, and using higher-efficiency
heating and cooling equipment.
The construction goal for occupancy
is early January, and, if the builders really work at things, that
goal may be achieved. In addition to looking at the above-described
environmental options, Court authorities have expressed strong interest
in considering any possible steps that might be taken to reach this
goal.
|
|
|
|
|
|
|
|
|