Traffic Impacts and Analysis
Addressing the traffic impacts of the Trade Center
Park (TCP) project has always been a major concern in this development.
Without safe and convenient access, the public could be at risk,
and no commercial development will ever fully succeed. The traffic
analysis for this project has a long history of study and review
in arriving at the current level of recommendations on significant
roadway improvements.
Initial traffic analyses were done in 2001 by Conley
Associates in conjunction with the project's MEPA submission. The
original study projected traffic impacts based on all office use,
and analysis was done at intersections determined at MEPA "scoping
sessions." Analyses were performed and roadway modifications
were proposed in close concert with MassHighway engineering review.
A final set of recommendations regarding the scope
of required improvements was outlined in a Section 61 Finding. This
document, issued on January 5, 2005, is MassHighway's authorization
notice to proceed with final engineering on an approved program
of roadway modifications (attached.)
Review
or Print Mass. Highway, Section 61 Finding.
The Boston engineering firm of Edwards and Kelcey,
Inc. (E & K) was then commissioned to perform the engineering
work involved in developing and documenting the final configuration
at the Main / Elm / Alfred and Sylvan (MEAS) intersection. Improvements
at this location were determined by MassHighway to be key in addressing
traffic impacts related to TCP's proposed development.
A full package of information was first submitted to the Woburn
Planning Board in August 2006 in conjunction with Trade Center Park's
Site Plan Review submission, including all traffic studies and plans
for the MEAS modifications. Subsequent city review, through the
Planning Director and City Engineer's office, resulted in a request
that the traffic study be updated to include five-year build and
no-build projections through 2011, along with revisiting traffic
counts at identified key intersections to verify current information.
Also, in August 2006, TCP was selected as the temporary relocation
site of Middlesex Superior Court. TCP was requested to review the
traffic implications associated with the inclusion of the courthouse
in the overall project proposal. Significant new analysis was made
to accurately project the anticipated courthouse traffic and its
impact on the intersection during peak hours.
Following that analysis, which was urged by the
Woburn Planning Board, the intersection of Winn Street and Beacon
Street in Burlington was identified as an additional area where
the traffic engineers felt substantial off-site work was in order.
This Burlington work, and also further modifications in Woburn to
all four quadrants of the Route 38 rotary, were submitted to the
Woburn Planning Board on December 7, 2006.
Finally, the Planning Board requested that the Woburn's
traffic consultant, Vanasse Hangen Brustlin, Inc (VHB), perform
a full peer review of the overall traffic analysis to develop a
comprehensive set of recommendations that would fully address all
TCP project impacts. The VHB review culminated in the production
of a written report dated November 14, 2006, presented to the Planning
Board at the November 14 Public Hearing. In summary, the attached
report concludes that the E & K analysis has satisfactorily
addressed the impacts and delineates a scope of roadway modifications
recommended in conjunction with this project.
Click
here to Review or Print report from VHB.
|